Income
|
|
|
Corporate Contributions
|
$ 26,800.00
|
|
Gifts in Kind & Self Help
|
$ 242,937.98
|
|
Individual, Business Contributions
|
$ 193,966.46
|
|
Misc Revenue
|
$ 124,061.25
|
|
Total Income
|
$ 587,765.69
|
|
Expenses
|
|
|
Business Registration Fees
|
$ 58.00
|
|
Accounting Fees
|
$ 495.00
|
|
Outside Contract Services
|
$ 45,749.00
|
|
Books Subscriptions, Reference
|
$ 45.00
|
|
Postage, Mailing Service
|
$ 2,031.50
|
|
Printing and Copying
|
$ 918.17
|
|
Insurance
|
$ 488.37
|
|
Other Costs
|
$ 66,068.95
|
|
Other Expenses
|
$ 700.00
|
|
Total Expenses
|
$ 116,553.99
|
Construction Cost Breakout
As of: 15 April 2013
|
Kentucky National Guard Memorial Construction Cost Breakout
|
|
|
|
|
As of: 15 Apr 2013
|
|
|
|
|
|
Estimate
|
Paid
|
Balance
|
|
Design & Management Phase A, B, C & D (Bender Associates Architects) completion of construction documents and project management through construction completion (17,455). Includes Mech, Elec & Plumbing Eng srvcs by E-Tech Consultants PLLC ($6,250)
|
$ 29,405
|
$ 18,124
|
$ 11,281
|
|
W. H. Brown Assoc Site Survey & Plat for MOU
|
$ 3,600
|
$ 3,600
|
$ -
|
|
Soil Compaction Survey
|
$ 3,500
|
$ -
|
$ 3,500
|
|
Site Clearing Strip and stockpile topsoil; erosion / silt control
|
$ 22,871
|
$ -
|
$ 22,871
|
|
Earthwork Balanced cut & fill; QC testing
|
$ 10,385
|
$ -
|
$ 10,385
|
|
Asphalt Paving DGA sub base 8'; no 2 aggregate sub base 4"; binder course 3" surface course 1"; parking lot striping; HC core striping; HC parking symbols; conc testing / mix design
|
$ 37,524
|
$ -
|
$ 37,524
|
|
Concrete Paving Con walk 4'/4" base; conc curbs and gutter; cont testing / mix design
|
$ 44,846
|
$ -
|
$ 44,846
|
|
Brick and Stone Paving 8x8 brick pavers sand set; cut limestone paving extra hard grouted in place
|
$ 252,518
|
$ -
|
$ 252,518
|
|
Site Improvements Retaining walls stone 12" thk x 36" h; retaining wall reinf concrete 8" thk x 36" h; cut limestone wall capping; cast in place stairs reinf concrete 36" h x 9' w; park bench painted hot dip galvanized steel; flag poles aluminum
|
$ 111,708
|
$ -
|
$ 111,708
|
|
Landscape Plantings Bed prep till amend fertilize & mulch; furnish and place topsoil in planting beds 12"; shade trees 2" cal B&B; shrubs 18"-24"; perennials 1 gal @ 18" oc
|
$ 18,482
|
$ -
|
$ 18,482
|
|
Seeding / Sodding Place topsoil from stockpile and rough grade 6"; sodding & finish grading; seeding & finish grading
|
$ 24,725
|
$ -
|
$ 24,725
|
|
Signage KYNG Monument sign bronze letters 18" t; KYNG campaign plaques & pedestal (8); KYNG donor plaques cut stone & masonry pedestal; HC parking signs
|
$ 96,428
|
$ -
|
$ 96,428
|
|
Site Lighting Light poles 8' t; flag pole, monument & sign lighting; walkway lighting
|
$ 19,582
|
$ -
|
$ 19,582
|
|
Site Electric Utility Distribution Hand holes, electric service underground; pvc conduit
|
$ 8,723
|
$ -
|
$ 8,723
|
|
Self Help KYNG Rough Site Prep Drainage Improvement Self Help KYNG
|
$ 235,750
|
$ 235,750
|
$ -
|
|
Muldoon Memorials Memorial design and concept; Black granite wall panels; All lettering, engraving, etching and finish work of granite panels; The installation of the black granite wall panels; The installation of the bronze statue; Design drawing needed for lettering; Granite caps and inserts used in signage wall (Price lock expires 11 AUG 2013)
|
$ 201,763
|
$ 8,000
|
$ 193,763
|
|
Bronze statue Daniel Boone & rock base Bronze Maquette, 1/3 Scale Clay & Bronze, 125% Life-size Bronze Daniel Boone (Sculptor Wyatt Gragg)
|
$ 85,258
|
$ 15,850
|
$ 69,408
|
|
Cash in hand
|
|
$ 220,274
|
|
|
Total
|
$ 1,207,068
|
$ 501,598
|
$ 925,744
|
|
10% Contingency
|
$ 120,707
|
|
$ 120,707
|
|
Grand Total
|
$ 1,327,775
|
$ 501,598
|
$ 826,177
|
|
|
Estimate
|
Paid
|
Balance
|
|
Major components & estimates from Bender Opinion of Cost: 26 Jan 12
|
Status =
|
38%
|
|
As of 26 September 2012 - Based on latest available project construction estimates. |
 |